• MARCH 2019 •
Level 0 - Scheduled PC Date May 2019
Floor is currently being 1st fixed and plaster boarded with the exception of those units positioned where the site compound is. The units located where the site compound is, will be handed over last in may. Units outside of this area, could be handed over some weeks earlier. Floor is also awaiting windows, which are in manufacture and are due to commence late February.
Level 1 - Scheduled PC Date April 2019
Floor is currently awaiting windows to allow final plaster boarding and skimming. Windows are in manufacture and are due to commence late February.
Level 2
- Scheduled PC Date April 2019
Floor is currently awaiting windows to allow final plaster boarding and skimming. Windows are in manufacture and are due to commence mid-February.
Level 3 - Scheduled PC Date March 2019
Floor is currently being 2nd fixed along with plastering works with the exception of a small number of units which are missing windows. Windows are in manufacture and are due to commence mid-February. Units with windows could be handed over earlier than prescribed.
Level 4 - Scheduled PC Date March 2019
Floor is
currently being 2nd fixed and plastered with the exception of a
small number of units which will be completed after the window delivery late
February Kitchens and Bathrooms are on site ready for installation
Level 5 - Scheduled PC Date March 2019
Floor is currently being 2nd fixed and plastered. Kitchens and Bathrooms are on site ready for installation
Level 6 -
Scheduled PC Date March 2019
Floor is currently having kitchens installed and receiving final decorations. Bathrooms have been fitted
Level 7 - Scheduled PC Date February 2019Floor is currently having kitchens installed and receiving final decorations. Bathrooms have been fitted
Level 8 - 13 - Scheduled PC Date February 2019
Floor is complete and is now receiving final snagging and lock down but is unable to be handed over until staircases, lifts, entrances are complete and stats made live
Level 14 - Scheduled PC Date February 2019
Floor is ready for snagging before final dec with the exception of 1 room due to roof works taking place. Unable to be handed over until staircases, lifts, entrances are complete and stats made live
Level 15 - Scheduled PC Date March 2019
Unit is currently being 1st fixed and 1st side plaster boarded. Awaiting windows to complete
• FEBRUARY 2019 •
• ALTRINCHAM ADDRESS •
• email •
• HALE ADDRESS •
FORTIS GROUP
SUITE 4
RICHMOND HOUSE
HEATH ROAD
HALE
WA14 2XP
+44(0)161 974 5860
INFO@FORTISDEVELOPMENTS.COM
BANK HOUSE
OLD MARKET PLACE
ALTRINCHAM
WA14 4PA