• MARCH 2019 •

Level 0 - Scheduled PC Date May 2019

Floor is currently being 1st fixed and plaster boarded with the exception of those units positioned where the site compound is. The units located where the site compound is, will be handed over last in may. Units outside of this area, could be handed over some weeks earlier. Floor is also awaiting windows, which are in manufacture and are due to commence late February.

Level 1 - Scheduled PC Date April 2019 

Floor is currently awaiting windows to allow final plaster boarding and skimming. Windows are in manufacture and are due to commence late February.

Level 2 - Scheduled PC Date April 2019

Floor is currently awaiting windows to allow final plaster boarding and skimming. Windows are in manufacture and are due to commence mid-February.

Level 3 - Scheduled PC Date March 2019

Floor is currently being 2nd fixed along with plastering works with the exception of a small number of units which are missing windows. Windows are in manufacture and are due to commence mid-February. Units with windows could be handed over earlier than prescribed.

Level 4 - Scheduled PC Date March 2019

Floor is currently being 2nd fixed and plastered with the exception of a small number of units which will be completed after the window delivery late February Kitchens and Bathrooms are on site ready for installation

Level 5 - Scheduled PC Date March 2019

Floor is currently being 2nd fixed and plastered. Kitchens and Bathrooms are on site ready for installation

Level 6 - Scheduled PC Date March 2019

Floor is currently having kitchens installed and receiving final decorations. Bathrooms have been fitted

Level 7 - Scheduled PC Date February 2019

Floor is currently having kitchens installed and receiving final decorations. Bathrooms have been fitted

Level 8 - 13 - Scheduled PC Date February 2019 

Floor is complete and is now receiving final snagging and lock down but is unable to be handed over until staircases, lifts, entrances are complete and stats made live

Level 14 - Scheduled PC Date February 2019 

Floor is ready for snagging before final dec with the exception of 1 room due to roof works taking place. Unable to be handed over until staircases, lifts, entrances are complete and stats made live

Level 15 - Scheduled PC Date March 2019 
Unit is currently being 1st fixed and 1st side plaster boarded. Awaiting windows to complete
Next panel

• FEBRUARY 2019 •

Next panel

Next panel

• ALTRINCHAM ADDRESS •

• email •

• HALE ADDRESS •




FORTIS GROUP

SUITE 4

RICHMOND HOUSE

HEATH ROAD

HALE

WA14 2XP

+44(0)161 974 5860

INFO@FORTISDEVELOPMENTS.COM

BANK HOUSE

OLD MARKET PLACE

ALTRINCHAM

WA14 4PA