NOW UNDER CONSTRUCTION – BRIDGEWATER WHARF, SALFORD.

13th February 2020

Fortis Group are pleased to announce the commencement of Bridgewater Wharf; Fortis’ latest eight storey residential development, located in Salford, Greater Manchester.

The scheme will consist of 376 residential apartments, offering a range of studios, one/two/three-bedroom apartments and townhouses.

Residents will also have access to a private gym, cycle storage, communal lounge and onsite parking.

The enabling package is almost complete; structures are demolished, bulk earthwork materials are exported, all survey work and pre commencement matters has concluded, and hoardings are being erected.

Piling is scheduled to start on 24th February 2020 it will continue for 6-8 week.

Kieran Moore, director of Fortis Group, said: “Following the success of Bridgewater Gate and Bridgewater Point, our latest scheme will create new homes, continuing the regeneration of the local area.” 

Click here for more information on our current, and future developments in Greater Manchester. 